mirror of https://github.com/cncf/toc.git
What: Resolve open comments
Why: * improve transparency in comment to vote time frame * capture the announcement process This change addresses the need by: * detailing the length of time public comment is open * adding a 2 day window for converting from comment to voting * adding announcement step at the end Signed-off-by: Emily Fox <themoxiefoxatwork@gmail.com>
This commit is contained in:
parent
2a83a4e5d9
commit
fbe2cba4ae
|
@ -70,12 +70,14 @@ While the details of the process are described in detail further for Incubating
|
||||||
* Who: TOC Sponsor(s) and Project
|
* Who: TOC Sponsor(s) and Project
|
||||||
* Assuming all outstanding issues are resolved, the TOC opens an internal comment period, about 1 week, for other TOC members to perform an independent review and verify all areas of the project have been evaluated
|
* Assuming all outstanding issues are resolved, the TOC opens an internal comment period, about 1 week, for other TOC members to perform an independent review and verify all areas of the project have been evaluated
|
||||||
* Who: TOC Sponsor(s) and TOC
|
* Who: TOC Sponsor(s) and TOC
|
||||||
* If no further issues are identified, the TOC sponsor(s) open the public comment period on the TOC mailing list. The project is updated on the project board to 'Public Comment'.
|
* If no further issues are identified, the TOC sponsor(s) open the public comment period on the TOC mailing list. The project is updated on the project board to 'Public Comment' and **the public comment period is open for two weeks**.
|
||||||
* Who: TOC Sponsor(s)
|
* Who: TOC Sponsor(s)
|
||||||
* Provided not additional items are identified during the public comment period, the TOC opens voting on the mailing list. The project is updated on the project board to 'In Voting'.
|
* Provided no additional items are identified during the public comment period, the TOC opens voting on the mailing list shortly thereafter (usually about 2 days subject to availability). The project is updated on the project board to 'In Voting'.
|
||||||
* Who: Initiate - CNCF Support Staff for the TOC, Voting - TOC and community members
|
* Who: Initiate - CNCF Support Staff for the TOC, Voting - TOC and community members
|
||||||
* If the vote passes, the results are emailed and the project is placed in the 'Done' state on the project board.
|
* If the vote passes, the results are emailed and the project is placed in the 'Done' state on the project board.
|
||||||
* Who: CNCF Support Staff for the TOC
|
* Who: CNCF Support Staff for the TOC
|
||||||
|
* An announcement is made conveying the project name and its new level status.
|
||||||
|
* Who: CNCF
|
||||||
|
|
||||||
#### Incubation process
|
#### Incubation process
|
||||||
|
|
||||||
|
|