Releasing Knative
We release the components of Knative every 6 weeks. All of these components must be moved to the latest "release" of all shared dependencies prior to each release.
14 days prior to the release
Announce the imminent pkg cut
Announce on #general that pkg will be cut in a week.
7 days prior to the release
Announce the imminent release cut
Announce on #general that the release will be cut in a week and that additional caution should be used when merging big changes.
Collect release-notes
Make a copy of the last release notes document, empty it out and send it to the WG leads of the respective project (serving or eventing) to fill in. Coordinate with both serving and eventing leads.
Cut release-x.y in pkg and test-infra libraries
Shared dependencies like knative/pkg and knative/test-infra are kept
up-to-date nightly in each of the releasing repositories. To stabilize things
shortly before the release we cut the release-x.y branches on those 7 days
prior to the main release.
Both pkg and test-infra also need to pin each other's release branch. To do
that, edit hack/update-deps.sh in the respective repo on the newly created
branch to pin the respective branch. Then run
./hack/update-deps.sh --upgrade and commit the changes.
The change to hack/update-deps.sh will look like this:
diff --git a/hack/update-deps.sh b/hack/update-deps.sh
index a39fc858..0634362f 100755
--- a/hack/update-deps.sh
+++ b/hack/update-deps.sh
@@ -26,7 +26,7 @@ cd ${ROOT_DIR}
# The list of dependencies that we track at HEAD and periodically
# float forward in this repository.
FLOATING_DEPS=(
- "knative.dev/test-infra@master"
+ "knative.dev/test-infra@release-x.y"
)
# Parse flags to determine any we should pass to dep.
PR the changes to each repository respectively, prepending the PR title with
[RELEASE].
Pin pkg and test-infra in downstream repositories
Similar to how the pin between pkg and test-infra themselves work, all
downstream users must be pinned to the newly cut release-x.y branches on those
libraries. The changes to hack/update-deps.sh look similar to above, but in
most cases both dependencies will need to be pinned.
diff --git a/hack/update-deps.sh b/hack/update-deps.sh
index b277dd3ff..1989885ce 100755
--- a/hack/update-deps.sh
+++ b/hack/update-deps.sh
@@ -32,8 +32,8 @@ VERSION="master"
# The list of dependencies that we track at HEAD and periodically
# float forward in this repository.
FLOATING_DEPS=(
- "knative.dev/test-infra@${VERSION}"
- "knative.dev/pkg@${VERSION}"
+ "knative.dev/test-infra@release-x.y"
+ "knative.dev/pkg@release-x.y"
"knative.dev/caching@${VERSION}"
)
The downstream repositories this needs to happen on are:
- knative/caching
- knative/eventing-contrib
- knative/eventing
- knative/net-certmanager
- knative/net-contour
- knative/net-http01
- knative/net-istio
- knative/net-kourier
- knative/operator
- knative/serving
Apply the changes the the master branches, run
hack/update-deps.sh --upgrade (and potentially hack/update-codegen.sh if
necessary) and PR the changes to the master branch. Don't cut the release
branch yet.
Cut and pin caching
caching sees very little traffic, so we cut it 1 week prior to the actual
release to unblock the serving release (it depends on caching). Cut a
release-x.y branch and pin it in serving as shown above. You can potentially
collapse this pin with the pkg/test-infra pin to serving per step 2.
Verify nightly release automation is intact
The automation used to cut the actual releases is the very same as the automation used to cut nightly releases. Verify via testgrid that all relevant nightly releases are passing. If they are not coordinate with the relevant WG leads to fix them.
1 day prior to the release
Confirm readiness
Confirm with the respective WG leads that the release is imminent and obtain green light.
Day of the release
Cut release-x.y branches of serving and eventing
Create a release-x.y branch from master in both repositories. Wait for release
automation to kick in (runs on a 2 hour interval). Once the release automation
passed, it will create a release tag in both repositories. Enhance the
respective tags with the collected release-notes using the Github UI.
Pin serving and eventing releases in dependent repositories
After the tags for serving and eventing are created, their version needs
to be pinned in all repositories that depend on them.
For serving that is:
- knative/eventing-contrib
- knative/net-certmanager
- knative/net-contour
- knative/net-http01
- knative/net-istio
- knative/net-kourier
For eventing that is:
The pins are similar to step 5 above, but now we're pinning serving and
eventing respectively. Again, the pin PRs are sent against the master
branch of each repository respectively.
Cut release-x.y branches of all remaining repositories
After the pin PRs are merged, cut the release-x.y branch in each of the
remaining repositories (except operator):
- knative/eventing-contrib
- knative/net-certmanager
- knative/net-contour
- knative/net-http01
- knative/net-istio
- knative/net-kourier
Release automation will automatically pick up the branches and will likewise create the respective tags.
After the release
Revert all pins to pin master branches again
Revert all pins in all repositories to pin the master branches again, run
hack/update-deps.sh --upgrade and PR the changes.